Case Study

KDS Windsor

Industry

Project Location

Hendersonville, NC

Project Scope

9,121 SF Renovation

Cooper Construction renovated the office space at KDS Windsor in Hendersonville, North Carolina and rebuilt the front and right elevations of the building.

Outside, the panel rib facade came off along with the wall at the aluminum storefront, and a new facade overhang, stone masonry veneer and exterior lighting went on in their place.

Inside, the aluminum storefront system was modified, the finishes were replaced throughout, and the mechanical, electrical and plumbing systems were brought up to current code and performance. Cooper installed the HVAC itself. A ten ton Carrier rooftop gas pack unit went in on an adapter curb sized to the existing Lennox equipment, with a matching economizer and programmable thermostat, eighteen new register assemblies and forty existing ones reworked, exhaust fans and gas piping. Cooper added a mini split for the space that needed its own control.

The renovation covered 9,121 square feet and ran 88 work days. Cooper also built a new employee parking area with a reworked entry drive, and an outdoor pavilion carried as an alternate.