Case Study

Blue Ridge Community College Baseball Field Site Work

Industry

Education

Project Location

Flat Rock, NC

Concept rendering of the field, based on a 2019 aerial photograph.

Project Scope

Rough Grading, Water Line, Storm Drainage, Erosion Control

Cooper Construction prepared the ground for the baseball field at Blue Ridge Community College in Flat Rock, North Carolina, in 2002.

The college split the field among three contractors: one for the site, one for the playing field, and one for the buildings. Cooper had the site. That meant the work that has to be finished before a ballfield can go in: the water line, erosion control, rough grading to the architect's contours, and the storm drainage that carries rain off the field.

With three contractors on one site, each crew was waiting on the one before it. Cooper signed on May 3, 2002, and on June 26 reported its part 100 percent complete and handed the site over to the field contractor.

Start your Project Today